Lonestar Construction Group
Matthew Rosenbalm
Derrick Lee
Collins Chio
Haider Ali
Sponsor - Batson-Cook Texas LLC
Mentor - Finn Gosch
Dr. Al Attah
Dr. Kaur Kawalpreet
Our senior design project focuses on the planning, design, and construction management of a new softball stadium clubhouse intended to enhance the athletic experience for both players and spectators. The facility is envisioned as a modern, functional space that supports team operations while complementing the aesthetics of the surrounding sports complex. The clubhouse will include locker rooms, showers, offices for coaches, team meeting rooms, restrooms, storage areas, and a small concession or lounge space. Designed with durable, low maintenance materials, the structure will blend architectural appeal with cost efficiency, ensuring long-term sustainability and ease of upkeep.
Grace Design Studio is overseeing an 8,000-square-foot project with a contract value of $5,475,566. Construction is scheduled to run from April 1, 2025, through February 11, 2026. Key milestones include building dry-in on October 9, 2025, OH inspection on November 6, 2025, and permanent power on November 27, 2025. The facility will feature a concrete foundation with steel structural components and a standing metal roof system with insulation and underlayment. This project is being developed in addition to the newly built softball stadium. Overall, the project is moving forward with a clear timeline and defined milestones. Its structure and design elements indicate strong planning for long-term performance.


KAEE Builders LLC
Kyvonte Perkins
Amir Sharifisousa
Edwin Trejo Sanchez
Edgar Sanchez Castro
SEMA Construction - Sponsor
Cole Hyun, National Scheduler - Mentor
Dr. Aloysius Attah, P.E.
Dr. Saman Rashidyan, P.E.
Our senior design project is the 1-35 Denton County Project, Bridges 15 & 16. Our senior design project will be creating the cost, schedule, logistics, safety, and sustainability for these 2 bridges out of a mega project in Denton County that plans to modernize and renovate all 1-35. These 2 bridges will allow Windsor Rd to cross 1-35 without needing to get into the interstate. The bridges will consist of 5 lanes going Northbound, and 4 lanes going Southbound.
The purpose of these bridges is to accommodate the growing population in Denton and the increasing number of travelers going through Interstate 35. The reason 1-35 will go over Windsor is to allow future transportation to carry taller, bigger, and heavier vehicles such as Truckers carrying wind turbines. One of our biggest challenges is finding a solution to keep dirt from causing major issues on the highway during construction. Before the 2 bridges are open, they must be joined using robust engineering methods so they can act as 1 bridge and transfer energy between the two.


Eagle Landing Construction
Beterin Cabrera Corrales
Karen Velasquez Duron
TJ Johnson
CORE Construction
Madison Ampoe, APM - Mentor
Dr. Aloysius Attah, P.E.
Dr. Zhenhua Huang
Irving Fire Station 8 is currently under construction by Eagle Landing Construction and is being delivered through a LEED-oriented Construction Manager at Risk (CMAR) contract valued at almost $16 million. The project consists of approximately 19,500 square feet and is designed as a two-story, five-bay fire station. In addition to the main facility, the scope includes the construction of a firefighting boathouse at Lake Carolyn. The project duration is 16 months, with substantial completion scheduled for May 13, 2026.
The project has encountered several technical and managerial challenges throughout its life cycle. Significant site-related issues stem from Irving's expansive clay soils, which are susceptible to shrinage and swelling. To address these conditions, the foundation system incorporates 80-foot-deep concrete piers and a slab-on-void design, increasing both complexity and cost. Additional challenges include financial pressures resulting from unforeseen site conditions, coordination conflicts within mechanical, electrical, and plumbing (MEP) systems, discrepancies in construction documents, and change orders that place strain on project contingencies.

Drew McDonnell
Oliver Hernandez
Rodolfo Salas
Suleiman Abu-Suleiman
TX Morrow Construction (TXMC)
Breck Landry
Dr. Aloysius Attah, P.E.
For this senior design project, Celina I & II (alternatively known as The Ownsby Apartments) is being developed under the sponsorship of TX Morrow Construction (TXMC) and the guidance of Breck Landry.
Celina I is the first phase of the development and consists of four buildings. This phase has been completed and includes a primary structure that houses the leasing office, amenities, a pool, and residential units. This is building 1000 and will be reflected in the scale model. Celina II consists of five additional buildings and is currently being constructed. In November 2025, excavation activities, formwork, and initial foundation reinforcement have begun. Upon our second site visit in January 2026 framing on many of the buildings had begun. Phase two has 377 total units and is 448,441 square feet.
A primary focus of this project is the design and construction of a detailed scale model representing the main building from phase one (Building 1000). The model includes architectural and structural elements, such as framing details and floor plans to showcase interior amenity finishes.
In parallel with model construction, the team observed and documented the construction activities on phase two. Construction operations such as staging areas, jobsite logistics, scheduling, and budgeting were evaluated. The observations and findings from both the model development and phase two construction progress were implemented into the report. Including sections on business plan, logistics and jobsite layout, budget analysis, schedule, value engineering, sustainability, safety, risk assessment, and scale model design/construction.